Construction Update July 22-26
So much work behind the scenes just to get a floor poured!
This week, the construction crew is hard at work on the following:
- Continue coordination with structural, civil, and MEP-FP designs.
- Continue construction document and MEP permit submittal design sets.
- Continue bio-swale installation.
- Prep for first floor slab pour in office area.
- Continue rock subgrade installation for car parking area.
- Continue forming and installing rebar in casting slabs.
- Complete underground electric in office.
- Begin underground electric for site.
- Begin underground plumbing and trench drains in shop.
- Pour first concrete tilt panels at casting slab locations.
« BACK TO NEWS