Construction Update July 22-26

So much work behind the scenes just to get a floor poured! 

This week, the construction crew is hard at work on the following: 

  • Continue coordination with structural, civil, and MEP-FP designs.
  • Continue construction document and MEP permit submittal design sets.
  • Continue bio-swale installation.
  • Prep for first floor slab pour in office area.
  • Continue rock subgrade installation for car parking area.
  • Continue forming and installing rebar in casting slabs.
  • Complete underground electric in office.
  • Begin underground electric for site.
  • Begin underground plumbing and trench drains in shop.
  • Pour first concrete tilt panels at casting slab locations.

 


 

« BACK TO NEWS

 

ARTUR EXPRESS, INC.
4824 Park 370 Blvd
Hazelwood, MO 63042
Phone: (314) 714-3400
Toll-free: 1-800-487-4339
Fax: (314) 714-3401

Facebook Twitter LinkedIn LinkedIn


Association Logos Association Logos

HOME | ABOUT US | SERVICES & SOLUTIONS | REQUEST A QUOTE | AVAILABLE EQUIPMENT | CAREERS | ROUTES | CONTACT | NEWS | LOGIN

Copyright © 2020 Artur Express, Inc. All rights reserved. Web design by Visual Lure.